Case Studies
Real jobs, start to finish: what the client needed, what made it tricky, what we did and the result. Town or area only; clients and addresses are left out.
Case Studies
Real jobs from each of our services, start to finish, with new ones added every month. Every job here has its reports issued or certificates lodged. Town or area only; clients and addresses are left out. For a shorter list of everything we have done this year, see our recent projects.
Last updated: 15 November 2026.
U-value and condensation risk analysis: as-built extension roof, Hounslow
The project. A single-storey L-shaped extension to a house in Hounslow, west London, with two tiled pitched roofs: about 20° on the side and about 13° at the rear. The roofs were already built and finished, inside and out, when building control raised three points. A 50 mm ventilated gap is normally expected above insulation between rafters, and this roof had about 25 mm. They asked for a condensation risk analysis, a U-value calculation and a note on how the roof void is ventilated.
The challenge. Nothing could be opened up. Both roofs were covered above and below, so we had to work from what the owner could show us: the structural engineer's drawings (47 x 175 mm rafters at 400 mm centres), the owner's description of the products, and photos taken during the build. The build-up is the same on both roofs: a vapour-permeable (Type LR) breathable underlay, the 25 mm gap, 150 mm foil-faced PIR between the rafters, 25 mm foil-faced PIR under the rafters with taped joints as the vapour control layer, and 12.5 mm plasterboard. Some cable holes run through that layer at the light points.
What we did. One report for both roofs, ready for building control, with every assumption listed.
- U-value calculation to BS EN ISO 6946, following the BRE BR 443 conventions, including the rafter bridging and the screw fixings through the under-rafter board.
- Condensation risk analysis to BS EN ISO 13788, following BS 5250:2021, with a London monthly climate. We ran five cases: the roof as built in normal and kitchen humidity, the vapour control weakened by the cable holes, no vapour control at all in a colder and wetter climate, and the fix described below.
- A surface condensation and mould check (temperature factor, fRsi).
- A ventilation note for both pitches, saying whether high-level vents are needed.
The result. Condensation was not the problem. All five cases passed, with no harmful interstitial condensation and no mould risk (fRsi 0.97 against a limit of 0.70, or 0.85 in kitchen conditions). The 50 mm gap is the BS 5250 rule for high-resistance felts. With a vapour-permeable underlay and a taped foil vapour control layer, moisture leaves through the underlay, so the 25 mm gap is fine and no high-level ventilation is needed on either roof. That saved lifting the top tile courses to fit vents.
The U-value was the tight one: 0.17 W/m²K against the Part L limit of 0.15 for a new roof on an extension. We said so plainly and gave the two least disruptive ways to close the gap. The first is a SAP comparison for the extension, with no work on the roof. The second is to over-board the ceilings with insulated plasterboard of at least 40 mm PIR, which brings the roof to 0.13 W/m²K. We reran the condensation check for that fix, as part of the job, and it passes too. A 25 mm board would only just meet the limit, so we didn't recommend it. The one action on site either way: seal the cables where they pass through the ceiling.
The report went out the morning after we were instructed. Junctions such as the eaves and the rooflight trimmers weren't part of this job. When building control asks for those, we model them as PSI values and thermal bridging.
What we need from you. The roof or wall build-up: product names and thicknesses, rafter or stud size and spacing, the membrane or underlay, the vapour control layer, and the finish. Add building control's comments and, for work already built, any photos taken during the build. Email your build-ups or WhatsApp us for a free quote.
SAP, PSI values, Part G and energy statement: new self-build house, Tokers Green, Reading
The project. A new detached self-build house in Tokers Green, a village just north of Reading in South Oxfordshire. It is timber frame and all-electric, with an air source heat pump, MVHR, 4 kWp of solar PV split east and west, and a 9.5 kWh battery. The owner was varying the planning permission (a Section 73 application) to enlarge the house from about 140 m² to 175 m² and change the layout, roof and windows. That meant a new design-stage SAP, a new energy statement for the council's Policy DES10 and a Part G water calculation, all on the new drawings.
The challenge. Three things had to line up.
- The SAP, done fresh on our side, passed on carbon and primary energy, but the first run was short on the fabric energy efficiency target. A heat pump or solar panels can't help with that target, only the fabric can.
- The wall build-up on the drawings gave a much weaker U-value than the figure the owner had been quoted. We flagged it before finalising, and the frame was specified with a better insulation layer, with the maker's U-value calculation behind it.
- The design kept moving. The drawings went from Revision H to Revision M, with new window and door sizes, a smaller roof lantern and steel beams over the two bi-fold doors.
What we did.
- SAP calculations to SAP 10.2 from the owner's take-off, which we checked against the drawings, then reran for every revision.
- PSI value calculations: seven junction models in AutoPSI to BR 497. Ground floor, intermediate floor, timber lintel heads, two flat roof junctions, and the two steel bi-fold heads. The steel heads sit right under another junction, so we modelled each one together with the junction above, as BR 497 requires.
- A Part G water efficiency calculation against the 110 litre optional requirement, from the owner's fittings schedule.
- An energy statement following the energy hierarchy (Be Lean, Be Clean, Be Green, Be Seen), written against the council's DES10 policy and its March 2026 advice note.
The result. Every Part L 2021 test passes. The fabric energy efficiency came in at 42.19 against a target of 43.33 kWh/m² a year. The calculated PSI values were the biggest single lever for that. Every modelled junction came in well under the SAP default, and every fRsi is 0.87 or better against the 0.75 limit, so the risk of surface condensation and mould at those junctions is low. On their defaults, the two steel bi-fold heads alone would most likely have pushed the house back over the fabric target. Modelled, they came in at 0.080 and 0.064 W/mK.
Regulated CO₂ is 86.6% below a Part L 2021 baseline, from 1.53 to 0.21 tonnes a year. The council's DES10 target is a 50% cut against the older 2013 rules, which it treats as equal to 19% against Part L 2021, so the house is far above both. Space heating demand is 33.6 kWh/m² a year. Water use is 105.3 litres per person per day, under the 110 limit.
When the drawings moved to Revision M, we updated the SAP, the PSI values and the energy statement together and sent them back the same day the owner gave the go-ahead, so all three documents still matched. We'll take the house through to the as-built SAP and EPC, and recheck the steel heads once the engineer finalises the beams.
What we need from you. The drawings (plans, elevations and sections), the wall, floor and roof build-ups, the window and door U-values, the heating, hot water, ventilation and PV details, a section through each junction for the PSI values, and the sanitary fittings schedule for Part G. If the council has an energy policy, tell us which one. Email your drawings or WhatsApp us for a free quote.
TM59 overheating at completion: new end-of-terrace house, Mitcham
The project. A new three-storey, three-bedroom end-of-terrace house in Mitcham, south London, about 126 m². It has a living room at the front, a rear kitchen and dining room under a flat roof with a roof window and a wide glazed folding door to the garden, two bedrooms on the first floor and a third bedroom in the roof with a rear dormer. We had done the design-stage SAP. The house was then built and occupied before anyone looked at Part O. At completion, building control asked for an overheating assessment.
The challenge. By then the house was finished, so every option that is cheap at design stage had gone: window sizes, glazing spec, orientation and shading were all fixed. The simplified method wouldn't show a pass on this layout, so it had to be a TM59 dynamic model with the Approved Document O limits.
The first model showed two problem rooms.
- The ground-floor kitchen. The big glazed folding door lets in a lot of sun in the afternoon. Part O doesn't let you leave ground-floor windows open at night, because they are easy to get in through, so the heat built up in the day had no way out overnight.
- The bedroom in the roof. A small room under the roof with dormer windows, so not much air moves through it. It ran hot at night against the bedroom limit.
What we did. We built the house in DesignBuilder from the as-built drawings and the window openings the builder marked up, with a London 2020s weather file. Then we went through the fixes still open on a finished house, one at a time, with a rerun for each:
- how far each window opens, and whether upstairs windows can stay open at night,
- the real g-value of the glazing (how much sun it lets through), which has to come from the window supplier, not a guess,
- external shading, such as external blinds or shutters,
- mechanical purge ventilation for the room that still ran hot.
The lessons. Each fix on a finished house costs more and buys less than the same fix on paper. Lowering the g-value helps with overheating, but it also cuts useful winter sun, so it can push the SAP the wrong way. Opening the top bedroom's windows fully helped, but not enough on its own. Internal blinds and curtains don't count for Part O at all, because they depend on how people use them, so only external shading, glazing and ventilation can be relied on. On a built house, that often means adding mechanical ventilation.
Check overheating at design stage, alongside the SAP. A Part O simplified check takes days, not weeks. If it shows a problem, a smaller window, a different glass or an overhang costs very little before the frames are ordered.
What we need from you. Plans, elevations and sections, the window schedule with sizes, how far each window opens and the glazing g-value from the supplier, and the ventilation spec. Send them with the SAP drawings and we'll check Part O at the same time. Email your drawings or WhatsApp us for a free quote.
SAP calculations and EPCs: four-flat conversion, Southall
The project. A building in Southall, west London, converted into four flats of 38 to 62 m². The flats have electric heating and a heat pump hot water cylinder. The developer needed as-built SAP calculations and EPCs for building control sign-off.
The challenge. The first as-built SAPs were done before the flats had been air tested. Without a test result, SAP has to assume an air permeability of 15 m³/(h·m²), which is a poor figure and drags the rating down. On that basis the flats came out at 68 to 77, a mix of D and C.
What we did. A small flat loses a lot of points to the default figure, and a well-built conversion usually tests far better than 15. So the flats were air tested in July. The results were 4.00 to 4.83 m³/(h·m²), roughly a third of the default. We then re-ran the as-built SAPs with the measured results.
The result.
- Before the air test (default 15): 68 to 77, D and C.
- After the air test (4.00 to 4.83): 75 to 82, C and B.
Two of the flats moved up to a B. The as-built SAPs were reissued with the tested figures, giving the developer a clean set for building control.
The lesson for any conversion is simple: get the air test booked before the as-built SAP, not after. It costs far less than an upgrade and it is often the single biggest gain in the calculation. We can price the air tests with the SAPs, and booking them together saves on travel.
What we need from you. For as-built SAPs on a conversion, send us:
- the as-built floor plans, sections and elevations,
- the wall, floor and roof build-ups that were actually installed, and any changes from the design,
- window and door schedules with U-values,
- the heating and hot water details, with product datasheets,
- the air test certificates, if the flats have been tested,
- the design-stage SAPs, if someone else did them.
The more of this we have on day one, the fewer reruns, and the sooner the EPCs can go out.
We turn SAP calculations around in 3 working days once we have everything we need.
Need the same for your project? Email your drawings or WhatsApp us for a free quote.
Part G water efficiency: two new flats, Cricklewood
The project. Two new flats in Cricklewood, north-west London. The planning permission set the tighter water efficiency limit, the optional requirement of 110 litres per person per day, instead of the standard 125. The developer needed Part G water calculations for both flats to show building control the condition was met.
The challenge. The 110 litre limit leaves little room. It includes 5 litres per person per day for outside use, so the fittings inside the flat have to come in at about 105 or less. The flats are generously fitted: one has two showers and two basins, the other three of each. Every extra shower and basin pushes the figure up, so the specification had to be right first time, before anything was ordered.
What we did. We took the fittings schedule and ran the Part G calculation for each flat:
- WCs: dual flush, 5 and 3 litres.
- Basin taps: 4 litres a minute.
- Kitchen tap: 8 litres a minute.
- Showers: 8.5 litres a minute.
- No bath.
- Dishwasher: 1.25 litres per place setting.
- Washing machine: 6.5 litres per kilogram.
Showers are usually the biggest single use in a flat without a bath, so the shower flow rate does most of the work. 8.5 litres a minute is a comfortable shower, not a trickle, and it still keeps the total down. The low-flow basin taps and the dual flush WCs do the rest.
The result. Both flats came out at 102.1 litres per person per day against the 110 litre limit, including the 5 litres for outside use. That is a comfortable margin, so the developer can swap a fitting for a similar one without redoing the calculation, as long as the flow rates stay the same or lower.
The calculations were issued in January 2026, ready for the building control submission.
What we need from you. Send us the floor plans and the fittings schedule: WCs and flush volumes, taps and flow rates, showers and flow rates, bath capacity if there is one, and the dishwasher and washing machine if they are supplied. If you don't have a schedule yet, we can tell you which flow rates will pass, so you can pick the fittings to suit.
If your planning permission has a water condition, send us the fittings schedule with the drawings. Part G calculations start from £65+VAT and take 5 working days.
Need the same for your project? Email your drawings or WhatsApp us for a free quote.
Energy statement: three new terraced houses, Walthamstow
The project. Three new two-storey terraced houses in Walthamstow, east London, of 71 to 88 m² each. A planning condition asked for a report, before anyone moves in, showing that the houses cut carbon emissions by at least 35% compared with the 2013 Building Regulations. The client needed an energy statement to discharge the condition, together with the completion SAP calculations and the Part G water calculations. We had done the design-stage SAPs for the same houses the year before.
The challenge. The houses were already built, so the report had to describe what was on site, not what was on the drawings. The builder had changed the wall insulation from the design, and the houses had not been air tested yet. The report also follows the London energy hierarchy (Be Lean, Be Clean, Be Green, Be Seen), and on these houses the first step, Be Lean, shows no saving. A planning officer reading that without an explanation could easily reject the report.
What we did. Before modelling, we asked the design team what had changed on site and checked the wall change against the SAP model. We then ran the energy hierarchy for each house from the SAP 10.2 calculations:
- Be Lean: walls 0.12 W/m²K (54% better than the Part L limit), floors 0.09, windows 1.2 and doors 1.0, a design air permeability of 4 m³/(h·m²), and 100% LED lighting.
- Be Clean: the site is in a heat network priority area, but the nearest proposed network is about 200 m away and not built, so a connection is not feasible for three houses.
- Be Green: an air source heat pump in each house, with a seasonal efficiency of about 291%, heating radiators, underfloor heating and a 250 litre hot water cylinder. No gas on site.
- Be Seen: a smart meter, a heat pump energy display and a water meter in each house.
Why Be Lean shows no saving. The comparison house used by the method assumes a gas boiler at 92.3% efficiency and waste water heat recovery on the shower. No regular gas boiler on the SAP product database reaches 92.3%, and these houses have no waste water heat recovery. So Be Lean came out 9.5% above the baseline, even though the fabric beats every Part L limit and the fabric energy efficiency beats its target in all three houses. We explained this plainly in the report, so the officer can see it is a quirk of the method, not poor building.
The result.
- Carbon emissions: 2.62 tonnes a year at the Part L 2021 baseline, 1.06 tonnes as built.
- Saving: 59.6% on site, against the 35% the condition asks for.
- The condition measures against the 2013 Building Regulations, which are about 31% easier to beat than Part L 2021, so the real margin is larger still.
When the client’s team asked whether the Be Lean result put the condition at risk, the answer was already in the report: the condition only asks for the 35% reduction, and the houses beat it by a wide margin. The report also brings in the overheating and water results, so the officer has everything in one document.
We had the go-ahead on 21 October and issued the report two days later, ready to submit to discharge the condition. The completion SAPs will be made final once the air test results are in. If the measured result changes anything, we re-run the energy statement at no extra charge.
What we need from you. For an energy statement, send us:
- the planning decision notice, with the energy condition,
- the plans, sections and elevations,
- the wall, roof, floor, window and door specification,
- the heating, hot water and ventilation details,
- the SAP or SBEM calculations, if someone else has done them,
- the air test results, if the building has been tested.
Energy statements start from £600+VAT and take 5 working days. We can price the SAPs and water calculations in the same quote.
Need the same for your project? Email your drawings or WhatsApp us for a free quote.
PSI values and thermal bridging: new timber frame house, Tokers Green, Reading
The project. A new detached house in Tokers Green, just outside Reading. It's timber frame and all-electric, 175 m² over two floors, with a single-storey flat-roof extension at the back. The planning permission was being varied to enlarge the house from 140 to 175 m², so the design-stage SAP and the energy statement had to be redone on the new drawings.
The challenge. The new SAP passed on carbon and primary energy by a wide margin, but failed the fabric energy efficiency target: 45.41 kWh/m² a year against 43.57, about 4% short. That target only looks at the fabric, so a heat pump or solar panels can't close the gap.
Thermal bridges were 31.06 W/K of the heat loss, a y-value of 0.072. Most junctions were on government-approved values, and the new flat-roof junctions sat on the SAP defaults.
We gave the client the options with the saving for each. Triple-glazed bi-folds would save about 4 W/K, not enough on their own. Calculated PSI values on four junctions were the biggest single lever, and cheaper than changing the glazing.
What we did. We built a 2D model of each junction in AutoPSI, to BR 497 and BS EN ISO 10211, from the client's sketches, the timber frame maker's details and the wall build-up:
- E5 ground floor: beam and block with 150 mm PIR, aircrete blocks under the sole plate.
- E6 intermediate floor: the rim board zone, where the joists meet the wall.
- E2 window and door heads: timber lintels in the frame.
- E14 flat roof: the roof edge, and where the roof meets the first-floor wall above.
We checked every model by hand: heat in equals heat out, and the PSI value works back from the heat flow. Where two junctions sit closer together than the wall thickness, such as a bi-fold head right under the roof edge, BR 497 says they must be modelled together, so we didn't stretch a single-junction result over those lengths.
The roof window maker sent a PSI value too. It was the glass-to-frame value used inside the window's own U-value, not the PSI of the window fitted in the roof, so we didn't use it.
The result. Every junction came in well below the value it replaced:
- E5 ground floor: 0.160 down to 0.058 W/mK, fRsi 0.92.
- E6 intermediate floor: 0.070 down to 0.043, fRsi 0.95.
- E2 timber lintel heads: 0.300 down to 0.051, fRsi 0.90.
- E14 flat roof edge: 0.160 down to 0.069, fRsi 0.94.
- E14 roof meeting the wall above: 0.160 down to 0.006, fRsi 0.97.
On the 95 m of junctions we modelled, heat loss came down from 13.72 to 4.81 W/K, about 65% less. Every fRsi is well above the 0.75 minimum for homes, so the risk of surface condensation and mould at these junctions is low.
With the calculated values and the first-floor wall upgraded to 0.14 W/m²K, the y-value dropped from 0.072 to 0.05 and the house passed the fabric energy efficiency target, with every other Part L target met too. The results, the SAP and the energy statement went to the client the day after the go-ahead.
If your SAP is a few per cent short on fabric, look at the junctions before the glazing.
What we need from you. Send us:
- a section through each junction (a clear sketch is fine),
- the wall, floor and roof build-ups with product names,
- the lintel or beam over each opening,
- the floor plans and elevations, so we can measure the lengths,
- the SAP, if someone else did it.
We price PSI values by the number of different junctions, not the number of homes, and turn them around in 5 working days. One team for the junctions and the SAP. More on our PSI value calculations page.
Need the same for your project? Email your junction details or WhatsApp us for a free quote.
TM59 dynamic overheating: two new semi-detached houses, Reading
The project. A pair of new semi-detached houses in Caversham, Reading, each about 185 m² with three bedrooms and an open kitchen and living area. The developer needed a Part O overheating assessment for building control. The local plan also asks new homes to show they can cope with hotter summers.
The challenge. We always try the cheaper simplified method first. Here it failed on one point. The glazing was fine: 10.7% of the floor area, and 17.1% in the most glazed room, both inside the limits for a moderate-risk site with cross-ventilation. Bedroom openings passed too. But the simplified method also needs enough openable window area to purge heat from the whole house: 9% of the floor area. Each house needed 16.2 m² and the windows gave 13.11 m².
That left two options: redesign the windows, or prove the houses don't overheat with a dynamic model.
What we did. Rather than redesign the windows, we ran a TM59 dynamic model. The simplified method is a set of rules of thumb. A dynamic model looks at the actual house, room by room, hour by hour, through a full summer of weather data.
We built the model in DesignBuilder with the real specification:
- Walls 0.18, roof 0.14 to 0.11 and floor 0.11 W/m²K.
- Windows 1.5 W/m²K with internal blinds.
- Openable rooflights.
- Air permeability of 4 m³/(h·m²).
- Natural ventilation through openable windows, as the occupants would use them.
The two houses are identical, with the same orientation, so one model covers both.
The result. Every room passed TM59 with no design changes.
Criterion A, the hours a room is too warm, must be no more than 3%:
- Kitchen and living area: 1.62%
- Bedroom 1: 1.09%
- Bedroom 2: 1.30%
- Bedroom 3: 0.70%
Criterion B, bedrooms too warm at night, must be no more than 32 hours a year. Bedroom 3 came in at 15.5 hours.
No window changes, no extra cost to the build and a report building control could check. If the simplified method fails on your scheme, don't redesign yet: send it to us first. TM59 assessments start from £500+VAT and take 5 working days.
Need the same for your project? Email your drawings or WhatsApp us for a free quote.
Ventilation testing: house refurbishment, Chalfont St Giles
The project. A house in Chalfont St Giles, Buckinghamshire, with a garage conversion, internal alterations and a new layout. Building control needed proof that the kitchen, bathroom and WC extract fans actually move the air Part F asks for before they would sign the job off.
The challenge. Extract fans often fail on the day for reasons nobody sees on the drawings: long or kinked duct runs, flexible ducting squashed in a ceiling void, the wrong fan for the length of run, or a cooker hood vented into the loft instead of outside. A fan can be running and still fall short of the rate.
What we did. Our tester measured each fan at its terminal with a calibrated air flow meter and hood, the method building control expect, and compared the measured rate with the Part F minimum for that room:
- Kitchen with a cooker hood: 30 litres per second.
- Bathroom: 15 litres per second.
- WC: 6 litres per second.
The flow meter carries a current calibration certificate, which is included in the report so building control can check it.
The result. All three fans passed first time:
- Kitchen: 33.2 l/s against 30.
- Bathroom: 21.7 l/s against 15.
- WC: 10.2 l/s against 6.
The tests were done in September 2026 and the report went to the builder for the building control submission. No remedial work and no retest were needed.
What we need from you. To book a ventilation test, send us:
- the building regulations drawings, so we know which rooms have extract,
- the fan and cooker hood models, if you have them,
- a date when the fans are wired and running, the ducts are finished and the room doors are on.
If a fan does fall short, the report shows by how much, so the electrician knows whether it needs a faster setting, a different fan or a shorter duct run. Then we come back and retest that fan only.
If you are near the end of a job with new extract fans, book the test before the decorators finish, so any duct fix is cheap. Booking air, sound and ventilation tests together costs less, because we save on travel.
Need the same for your project? Email your drawings or WhatsApp us for a free quote.
Solar PV in SAP: large new house, Fulmer, Buckinghamshire
The project. A large new detached house in Fulmer, Buckinghamshire, of 2,008 m². The design used a heat pump, a large solar PV array and a very tight, well-insulated fabric. The client needed the as-built SAP calculation and EPC for building control sign-off.
The challenge. On a house this size the energy use is high, so the PV has to be sized and modelled properly to get the full benefit in the calculation. Orientation, pitch and overshading all change the PV output SAP will credit. Getting any of them wrong costs points.
What we did. We modelled the house as built:
- Solar PV: 64.80 kWp, facing south at a 30° pitch, with little or no overshading.
- Heating: ground-to-water heat pump with fan coil units.
- Hot water: a 1,500 litre cylinder with waste water heat recovery.
- Fabric: walls 0.09, roof 0.08 and floor 0.15 W/m²K.
- Air permeability: 1.9 m³/(h·m²), as tested.
The result. The house rated A (98). Its emission rate came out at 1.61 kgCO₂/m² a year against a target of 22.33, about 93% below the Part L target. The fabric energy efficiency was about 24% better than its target too.
Why the modelling matters. SAP credits PV by its peak output, orientation, pitch and shading. A south-facing array at 30° with no overshading gets close to the full credit. The same panels facing east or west, or shaded by trees or a chimney, get noticeably less. That is why we model the array exactly as it is fitted, from the installer's details and the drawings, not from a rule of thumb. On a house with this much demand, the PV and the heat pump together are what take the emission rate so far below the target.
What we need from you. For PV in an as-built SAP, send us the MCS certificate or the installer's commissioning sheet, the panel and inverter datasheets, the roof plan showing the array, and anything that shades it.
We size PV in the SAP for homes, the SBEM for new commercial buildings and the commercial EPC for existing ones. If you want panels fitted, we can introduce you to a trusted MCS-certified installer. We may receive an introduction fee from the installer.
Need the same for your project? Email your drawings or WhatsApp us for a free quote.
SBEM and BRUKL: new ground-floor shop unit, Harrow
The project. A new 136 m² shop unit on the ground floor of a new building in Harrow, north-west London. The unit is all-electric: panel heaters, an air-source split system for heating and cooling, instant electric hot water, LED lighting and solar PV. The contractor needed the as-built SBEM calculation and BRUKL report to show building control the unit met Part L.
The challenge. Since the 2021 Part L, a non-domestic building has to pass two targets, not one: its carbon emission rate and its primary energy rate. Both are compared with a "notional" version of the same unit. Small all-electric units can pass the carbon target and still struggle on primary energy, because electric panel heaters use a lot of it. The as-built model also has to match what was actually installed, not the design drawings.
What we did. We built the SBEM model from the as-built drawings and the installed specification:
- Walls 0.19 W/m²K against a limit of 0.26.
- Ground floor 0.17 against a limit of 0.18.
- Windows 1.2 against a limit of 1.6.
- Air permeability 3.8 m³/(h·m²) against a limit of 8.
- LED lighting at 100 lumens per watt.
- The air-source split system for heating and cooling, plus the electric panel heaters.
- The solar PV.
We also checked the solar gain limits, which passed comfortably.
The result. The unit passed both Part L targets:
- Carbon: 5.15 kgCO₂/m² a year against a target of 5.48.
- Primary energy: 54 kWh/m² a year against a target of 57.78.
The margins are about 6% on each, which is normal for a well-specified small unit. The good fabric, the tight air test and the PV did the work. We issued the BRUKL report a few days after receiving the information, ready for building control.
What we need from you. For an as-built SBEM, send us:
- the as-built plans, sections and elevations,
- the wall, floor, roof and glazing specification as installed,
- the heating, cooling, hot water and ventilation equipment, with datasheets,
- the lighting schedule,
- the air test certificate,
- the PV details, if there are panels.
SBEM calculations with the BRUKL report and EPC start from £400+VAT, and take 3 working days for small units like this one.
Need the same for your project? Email your drawings or WhatsApp us for a free quote.
Commercial EPC: health clinic, Hammersmith
The project. A 219 m² health clinic in Hammersmith, west London, air conditioned and all-electric. The landlord needed a new commercial EPC for the building.
The challenge. Commercial EPCs are rated on a scale where 50 is the line between B and C. A clinic like this has a lot of air conditioning and lighting, and every system has to be entered correctly to get a fair rating. Small errors in the inputs, such as the wrong lighting type, cooling efficiency or hot water system, can easily cost a band. For a landlord that matters: the rating goes on the letting particulars, and the minimum energy rules for letting commercial property are getting tighter.
What we did. We provide commercial EPCs for all non-domestic buildings, up to Level 4. For this clinic we modelled the building's actual construction and systems:
- the zones and what each one is used for,
- the air conditioning,
- the lighting, zone by zone,
- the hot water,
- the building fabric and glazing.
The building was modelled at Level 3, and we checked the results before lodging.
The result. The clinic rated B (50), right on the B side of the line.
- Emission rate: 13.53 kgCO₂/m² a year.
- The same building built new today would rate A (14).
- A typical existing building of this type would rate C (56).
So the clinic does better than the typical existing building of its type, and is well above the E minimum for letting. The EPC was lodged the day after the assessment and is valid until October 2036. It came with the recommendations report, which lists the improvements that would push the rating further into the B band, so the landlord has a plan ready if the rules tighten.
What we need from you. For a commercial EPC, send us the floor plans if you have them, what each area is used for, and access details. If you are planning works, tell us. An EPC done after the works can be quite different.
Booking a commercial EPC with a TM44 costs less, because we save on travel. Commercial EPCs take 3 working days for small buildings and 5 for larger ones.
Need the same for your building? Email your drawings or WhatsApp us for a free quote.
Part O overheating: three terraced houses, Slough
The project. Three new-build terraced houses in Slough, all the same design: 103 m² each, with two bedrooms and most of the glazing on the west side. Building control needed a Part O overheating report for every house before sign-off, and the client wanted the cheapest route that would actually pass.
The challenge. Part O gives you two routes. The simplified method is quick and cheap, but it only works if the glazing and the openings stay inside fixed limits. A dynamic model (TM59) can pass almost any design, but it costs more and takes longer. The client asked us which one this scheme needed before spending anything.
Slough is a moderate-risk location, and these houses have windows on both sides, so they count as cross-ventilated. That sets the limits. The biggest area of glazing faces west, which is the hardest side, because the low afternoon sun heats rooms the most. Approved Document O allows west-facing glazing of no more than 11% of the floor area. These houses came in at 10.87%. Too close to guess, so we checked it properly.
What we did. We looked at the drawings first and gave a straight answer: the simplified method should work here, and if it didn't, the next step would be a dynamic model. The client gave us the go-ahead for the simplified method on all three houses.
We then ran the simplified method on all three houses:
- Glazing for the whole house: 10.87% of the floor area against the 11% west-facing limit.
- The most glazed room (31.37 m²): 16.58% against a limit of 22%.
- Openings to purge heat: the house needs 9.27 m² of free area (9% of the floor area). The windows give 9.55 m².
- Bedrooms at night: each needs 4% of its floor area as openings. The main bedroom has 1.67 m² against 0.58 m², the second bedroom 1.00 m² against 0.35 m².
The same report covers the Part 3 requirements for those openings: noise, security and protection from falling. So when building control asked for the Part 3 declarations, the answer was already in the report and the client only had to forward it.
The result. All three houses passed the Part O simplified method. No dynamic model was needed, which saved the client the extra fee and the extra time. We received the plans in the afternoon and issued the three reports the next working day, and building control signed them off.
If your west or south glazing is close to the limit, send us the drawings before the windows are ordered. A small change to one window size at design stage is far cheaper than a dynamic model later.
Need the same for your project? Email your drawings or WhatsApp us for a free quote.
Air and sound testing: five flats above a commercial unit, Southampton
The project. A conversion of the upper floors of a city-centre building in Southampton into five flats, above a first-floor restaurant that was being refurbished at the time. Building control needed a pre-completion air tightness test on every flat and Part E sound tests before signing the conversion off.
The challenge. Sound testing a conversion over a commercial unit means testing two kinds of separation: the floors between the restaurant and the flats, and the walls between the flats themselves. Those separating floors are often where conversions struggle, because noise from a busy restaurant is exactly what the new residents will complain about.
The timing was tight too. The air tests were added to the booking a few days before the test date, so both sets of tests had to be done on the same day.
What we did. We agreed the test plan with the designer the day before:
- Two airborne sound tests on the separating floor between the restaurant and the flats above it.
- Two airborne sound tests on the timber stud separating walls between flats (full-fill insulation with two layers of sound board).
- An air tightness test on all five flats.
Putting the air tests on the same booking meant the client paid for one trip, not two. Our air testers are registered with the Elmhurst Airtightness Scheme and our sound testers with SITMA. As a conversion, the flats were tested against a design air permeability of 8 m³/(h·m²) at 50 Pa, using the blower door method to ATTMA TSL1.
The result. Everything passed first time, with no remedial work and no retests.
Air tightness, against 8 m³/(h·m²):
- Flat 1: 4.22
- Flat 2: 3.19
- Flat 3: 3.15
- Flat 4: 4.75
- Flat 5: 7.77
Sound insulation, against a minimum of 43 dB (DnT,w + Ctr):
- Restaurant to the flats above (precast concrete floor): 54 dB and 56 dB.
- Between flats (timber stud walls): 48 dB and 45 dB.
The two floors over the restaurant gave the best results on the job, 11 and 13 dB better than the minimum. Flat 5 had the tightest margin on air, at 7.77. The reports went to the client two working days after the tests.
Booking air, sound and ventilation tests together costs less, because we save on travel.
Need the same for your project? Email your drawings or WhatsApp us for a free quote.
TM44 air conditioning inspection: document storage warehouse, Park Royal
The project. A 1,195 m² document storage warehouse in Park Royal, north-west London. Any building with air conditioning of more than 12 kW in total needs a TM44 inspection at least every five years, and the report has to be lodged on the government register to be valid. The owner needed a new inspection and a lodged report to stay compliant. This was one of several sites we have inspected for the same owner.
The challenge. This was a Level 4 inspection, not a simple one. The building has three separate air conditioning systems, 127 kW of rated output in total:
- split units,
- a multi-split system, where one outdoor unit serves several indoor units,
- close control units in the storage vaults.
Close control units hold the temperature and humidity steady for the stored documents, so they have to be inspected as a system in their own right, not lumped in with the comfort cooling.
The paperwork was late too. The floor plans and the F-gas records only came through on the day the inspection was booked.
What we did. We kept the booking and our assessors inspected all three systems as planned. We provide simple and complex (Level 3 and Level 4) TM44 inspections across the whole UK, including Northern Ireland.
For each system the report looks at:
- how efficient the system is likely to be, and how to improve it,
- whether it is the right size for the cooling load of the space it serves,
- its controls, and how well they match the way the building is used,
- practical recommendations the owner and their maintenance contractor can act on.
We checked the draft report before lodging it, because once a TM44 report is lodged it can't be changed free of charge.
The result. The TM44 inspection report and certificate were lodged on the government register on 22 October 2026, covering all three systems and the full 127 kW. The owner now has a valid report on record for the next five years and a clear list of improvements to plan into their maintenance.
Booking a TM44 and commercial EPC together costs less, because we save on travel.
Need the same for your building? Email your drawings or WhatsApp us for a free quote.
Send Us Your Drawings
Have a similar project? Send us your drawings and we will come back with a price and a turnaround time.
